Scope of the Contract:
Construction of a crusher at the Limestone Quarry as part of the investment project: "Construction of a crushing and transport system for excavated earth and rock masses from the Pajęczno-Makowiska deposit to the Niwiska border with discharge into the excavation site."
As part of the contract, Elproinstal carried out the following work:
Delivery and installation of a 6-panel technology switchboard for the Crusher building.
Delivery and installation of a 6-panel technology switchboard for the transport and transfer system to the main conveyor.
Delivery and installation of a 1-panel communication switchboard for the entire Crusher technology,
• Delivery and installation of 35 VOS-type motor switches.Delivery and installation of control boxes for belt scrapers.
Installation of pre-start warning systems and emergency stop switches.
Cabling works.
Construction of supporting structures for cable trestles.
Installation of 614 primary and emergency lighting fixtures.